﻿GET_GEVOMechL2_09_01_01_46 - STEP-BY-STEP Cont Screen
1
00:00:00,000 --> 00:00:16,875
<b>Caution:</b> Before completing the alternator electrical connections, inspect the alternator collector rings, brushes, and brush holders as discussed in the Collector Ring Inspection, Brush Inspection, Brush Holder/Collector Ring Cover Inspection sections, respectively.

2
00:00:16,875 --> 00:00:22,875
Bus bars, insulated studs, and brush holder mounting posts should also be closely examined.

3
00:00:22,875 --> 00:00:29,792
Failure to perform final inspections may result in premature failure and/or equipment damage.

4
00:00:29,792 --> 00:00:37,125
30. Re-connect the electrical connections, including the main and auxiliary output and input wiring.

5
00:00:37,125 --> 00:00:51,250
31. Torque the aux stator cable terminals to 23 +2/-1 lb.-ft. (31 +3/-1 Nm) and torque all other hardware to the correct torque value.

6
00:00:51,250 --> 00:00:59,125
<b>Warning:</b> The blower cab weighs approximately 4,000 lbs. (1,814 kg).

7
00:00:59,125 --> 00:01:03,417
Ensure the lifting device, cables, and straps are adequate.

8
00:01:03,417 --> 00:01:07,708
Failure to do so may result in personal injury or death.

9
00:01:07,708 --> 00:01:11,333
32. Reinstall the blower cab.

10
00:01:11,333 --> 00:01:18,167
33. Reinstall the hidden bolt removed earlier and torque to appropriate torque values.

11
00:01:18,167 --> 00:01:25,875
<b>Warning:</b> The corner air duct weighs approximately 260 lbs. (120 kg).

12
00:01:25,875 --> 00:01:30,208
Ensure the lifting device, cables, and straps are adequate.

13
00:01:30,208 --> 00:01:34,708
Failure to do so may result in personal injury or death.

14
00:01:34,708 --> 00:01:40,792
34. Reinstall the corner duct to the B-side of the locomotive as follows:

15
00:01:40,792 --> 00:01:47,750
a. Properly attach the lifting device to the duct, then lift and place it in position.

16
00:01:47,750 --> 00:01:53,917
b. Reinstall the mounting latch hardware and torque to appropriate torque values.

17
00:01:53,917 --> 00:02:03,208
c. Reinstall the bolt, washers and lockwashers connecting the duct to the blower cab and torque to appropriate torque values.

18
00:02:03,208 --> 00:02:09,833
35. Reinstall all applicable bolts and cooling air connections to the blower cab.