﻿GET_GEVOMechL2_07_01_01_75 - STEP-BY-STEP Cont Screen
1
00:00:00,000 --> 00:00:14,542
8. Install the lateral dampers to the platform, with the shorter bolt at the bottom, and torque the bolts to 118 ± 6 lb.-ft. (160 ± 8 Nm).

2
00:00:14,542 --> 00:00:21,292
<b>Note: </b>Ensure that “BELOW” stamped onto the body is on the bottom side of the lowest end of the damper.

3
00:00:21,292 --> 00:00:33,875
9. Install the yaw dampers to the platform and torque the bolts to 208 ± 11 lb.-ft. (282 ± 15 Nm).

4
00:00:33,875 --> 00:00:40,875
<b>Note: </b>Ensure that “BELOW” stamped onto the body is on the bottom side of the lowest end of the damper.

5
00:00:40,875 --> 00:00:46,833
10. If installing the long-hood end truck, connect the hand brake chain.

6
00:00:46,833 --> 00:00:57,417
11. Install the hoses from the sand pipes on the platform to the sander brackets on the trucks and install the hoses for flange lubricators, if used.

7
00:00:57,417 --> 00:01:04,292
12. Connect the axle alternator cable to the junction box on the alternator, if used.

8
00:01:04,292 --> 00:01:17,417
13. Install the traction motor air duct to each of the traction motors and torque the bolts to 58 ± 3 lb.-ft. (80 ± 5 Nm).

9
00:01:17,417 --> 00:01:22,833
14. Connect the ground cable between the truck and the platform.