﻿GET_GEVOMechL2_03_01_01_73 - STEP-BY-STEP Screen
1
00:00:00,000 --> 00:00:06,000
Typical steps to install one of the radiator banks on the locomotive are as follows:

2
00:00:06,000 --> 00:00:16,958
<b>Warning:</b> To prevent personal injury and potential equipment damage, ensure that the engine cannot be started before removing, installing, or adjusting any components.

3
00:00:16,958 --> 00:00:20,083
Open the BS to prevent starting attempts.

4
00:00:20,083 --> 00:00:25,333
Also, place the FPB and the LCCB in the OFF position.

5
00:00:25,333 --> 00:00:29,000
Apply a warning tag to the EC switch.

6
00:00:29,000 --> 00:00:39,958
<b>Warning:</b> A radiator bank with the shutter assembly mounted to it weighs approximately 2355 lbs. (1070 kg).

7
00:00:39,958 --> 00:00:42,958
Ensure that the lifting device is adequate.

8
00:00:42,958 --> 00:00:47,625
Failure to do so may result in personal injury or death.

9
00:00:47,625 --> 00:00:57,000
1. Attach the lifting device to the two lifting lugs, then carefully lift the radiator bank and place it into the radiator cab.

10
00:00:57,000 --> 00:01:03,917
2. Install and align the Victaulic couplings and pipes in the inlet and discharge headers.

11
00:01:03,917 --> 00:01:13,917
<b>Note:</b> For additional information on assembly and installation of the Victaulic couplings, refer to the Victaulic Coupling Installation section of this module.

12
00:01:13,917 --> 00:01:17,625
3. Connect the short-hood vent lines.

13
00:01:17,625 --> 00:01:24,083
4. Reconnect the air lines, two per shutter, attached to the shutter cylinders.

14
00:01:24,083 --> 00:01:30,333
<b>Note:</b> All Evolution Series locomotives are not equipped with the radiator shutter assembly.

15
00:01:30,333 --> 00:01:34,917
Some, in place of the radiator shutter assembly, have a covering grate.

16
00:01:34,917 --> 00:01:44,375
For these locomotives, remove all sets of clamps, lockwashers, washers, and bolts that secure the grate to the assembly.

17
00:01:44,375 --> 00:02:05,000
5. Using the four previously removed and saved hold-down hex-head bolts, washers, and plates, fasten the radiator bank to the center-vee mounting channel, then tighten the bolts to 110-120 lb.-ft. (150-162 Nm).