﻿GET_GEVOMechL2_03_01_01_73 - STEP-BY-STEP Cont Screen
1
00:00:00,000 --> 00:00:08,625
<b>Warning:</b> The WBIC core weighs approximately 550 lbs. (250 kg).

2
00:00:08,625 --> 00:00:11,583
Ensure that the lifting device is adequate.

3
00:00:11,583 --> 00:00:15,375
Failure to do so may result in personal injury or death.

4
00:00:15,375 --> 00:00:28,167
7. Install the puller tool (PSB P5205) onto the B-side of the locomotive for removing the intercooler core, as follows:

5
00:00:28,167 --> 00:00:33,125
a. Install the support plate to the locomotive carbody.

6
00:00:33,125 --> 00:00:39,000
b. Set the support stand on the handrail allowing it to sit on the catwalk.

7
00:00:39,000 --> 00:00:47,250
<b>Warning:</b> The intercooler core cradle support weighs approximately 100 lbs. (45 kg).

8
00:00:47,250 --> 00:00:52,250
Ensure that the lifting device, cables, and straps are adequate.

9
00:00:52,250 --> 00:00:56,417
Failure to do so may result in personal injury or death.

10
00:00:56,417 --> 00:01:01,833
c. Install the cradle support legs using ball lock pins.

11
00:01:01,833 --> 00:01:10,833
d. Install the cradle support using ball lock pins, then adjust the support so it is level with the bottom of the intercooler core.

12
00:01:10,833 --> 00:01:17,042
e. Install the puller tool puller bar onto the end of the intercooler core.