5. Insert the pipe with one person holding the pipe in position while another person carefully slides the gasket into place.

2
00:00:08,958 --> 00:00:18,125
<b>Note:</b> To ensure that the gasket is properly located on the pipe, both corners of the gasket's sealing surface must be exposed.

3
00:00:18,125 --> 00:00:28,583
<b>Note:</b> There should be approximately a 0.125-inch (3.18 mm) gap between the pipe ends to allow for expansion.

4
00:00:28,583 --> 00:00:45,417
The gap between the piping lengths can be adjusted by loosening the four 0.5-inch (12.7 mm) bolts at the flange at one end of the pipe, moving the pipe into the desired location, then retightening the bolts to seal the pipe.

5
00:00:45,417 --> 00:00:56,542
6. Install the coupling halves, then install the bolts and nuts ensuring that the oval under each bolt head is mated into the recessed oval in the coupling half.

6
00:00:56,542 --> 00:01:03,375
7. Tighten the nuts until there is a metal-to-metal contact between the coupling halves.

7
00:01:03,375 --> 00:01:06,625
8. Check the system for leaks.

8
00:01:06,625 --> 00:01:16,125
9. Torque the Victaulic coupling bolts to 70-80 lb.-ft. (95-108 Nm).

9
00:01:16,125 --> 00:01:24,750
10. Ensure that the Victaulic couplings are pointed out, mounted horizontally with respect to the split line of the coupling.

10
00:01:24,750 --> 00:01:31,375
<b>Note:</b> Some dripping of lubricant from pipe joints may occur as the engine and piping warms up.

11
00:01:31,375 --> 00:01:37,208
This should not cause a concern unless you see evidence of joint leakage.