Pre-Lube Pump and Motor Assembly Removal

2
00:00:03,208 --> 00:00:06,708
1. Drain the oil from the lubricating oil system.

3
00:00:06,708 --> 00:00:13,667
2. Remove the applicable locomotive handrail section to allow for pre-lube pump and motor assembly removal.

4
00:00:13,667 --> 00:00:18,917
3. Disconnect the inlet and outlet hoses from the pre-lube pump JIC fittings.

5
00:00:18,917 --> 00:00:25,500
4. Remove the terminal junction box cover on the side of the pre-lube motor by removing the six screws.

6
00:00:25,500 --> 00:00:30,667
5. Remove the wire lugs from the terminals inside the terminal junction box.

7
00:00:30,667 --> 00:00:39,750
6. Disconnect the conduit fitting on the top of the terminal junction box and pull the plastic conduit and wires from the pre-lube pump and motor assembly.

8
00:00:39,750 --> 00:00:50,125
7. Re-install the cover on the terminal junction box and torque the six screws to 20-25 lb.-in (2.26-2.82 Nm).

9
00:00:50,125 --> 00:00:57,333
8. Remove the four mounting bolts that secure the pre-lube pump and motor assembly to the floor of the radiator cab.

10
00:00:57,333 --> 00:01:07,542
9. With the appropriate lifting device, gently slide the pre-lube pump and motor assembly from the radiator cab, and then lift and remove the assembly from the walkway.

11
00:01:07,542 --> 00:01:10,708
Pre-Lube Pump and Motor Assembly Installation

12
00:01:10,708 --> 00:01:16,583
1. With an appropriate lifting device, place the pre-lube pump assembly on the radiator cab.

13
00:01:16,583 --> 00:01:23,708
2. Install the four mounting bolts that secure the pre-lube pump and motor assembly to the floor of the radiator cab.

14
00:01:23,708 --> 00:01:31,417
3. Torque the four mounting bolts to 55-62 lb.-ft. (74.5-84 Nm).

15
00:01:31,417 --> 00:01:38,417
4. Re-install the inlet and outlet hoses to the JIC fittings on the pre-lube pump and tighten until snug.

16
00:01:38,417 --> 00:01:48,042
5. Torque the inlet hose to the inlet JIC fitting to 210-220 lb.-ft. (284-298 Nm).

17
00:01:48,042 --> 00:01:57,917
6. Torque the outlet hose to the outlet JIC fitting to 140-150 lb.-ft. (190-203 Nm).

18
00:01:57,917 --> 00:02:04,333
7. Remove the terminal junction box cover on the side of the pre-lube motor by removing the six screws.

19
00:02:04,333 --> 00:02:11,667
8. Insert the wires and plastic conduit through the top conduit hole in the terminal junction box and tighten the conduit fitting.

20
00:02:11,667 --> 00:02:24,125
9. Connect the wire lugs into the terminals inside the terminal junction box and tighten to 120-140 lb.-in (13.56-15.82 Nm).

21
00:02:24,125 --> 00:02:35,083
10. Re-install the cover on the terminal junction box and torque the six screws to 20-25 lb.-in (2.26-2.82 Nm).

22
00:02:35,083 --> 00:02:41,333
11. Install the locomotive handrail section that was removed during pre-lube pump and motor assembly removal.

23
00:02:41,333 --> 00:02:43,875
12. Fill the lubricating oil system.

24
00:02:43,875 --> 00:02:46,250
Pre-Lube Check Valve Replacement

25
00:02:46,250 --> 00:02:56,458
1. Remove the pre-lube supply hose from the check valve using a TESCO T87340 2 ¼-inch crow’s foot and breaker bar.

26
00:02:56,458 --> 00:03:04,583
2. Remove the old check valve using a TESCO T87330 2-inch crow’s foot and breaker bar.

27
00:03:04,583 --> 00:03:11,750
3. Insert and rotate the new check valve a few turns by hand to verify that the thread-o-let is not oval.

28
00:03:11,750 --> 00:03:23,875
4. If the check valve binds or if the thread-o-let has an oval shape, either replace the pipe or re-tap the thread-o-let with a 1.5-inch NPT tap as follows:

29
00:03:23,875 --> 00:03:30,667
a. Remove the Victaulic coupling, and then remove the oil inlet pipe flange assembly from the left side of the oil cooler.

30
00:03:30,667 --> 00:03:40,458
b. If re-tapping the thread-o-let, use the 1.5-inch NPT tap to re-tap the threads, then clean the pipe of metal shavings before reinstalling.

31
00:03:40,458 --> 00:03:54,875
c. With Vic-Lube applied to the Victaulic coupling seals, and the Victaulic coupling mounted horizontally with respect to the split line of the coupling, reinstall the re-tapped or replacement oil inlet pipe flange assembly to the left side of the oil cooler.

32
00:03:54,875 --> 00:04:05,083
5. Install the replacement check valve, then torque to the appropriate value with a TESCO T87330 2-inch open end crow’s foot.

33
00:04:05,083 --> 00:04:17,917
6. With no Vic-Lube applied to the JIC hose fitting, use a TESCO T87340 2 ¼-inch crow’s foot to torque the hose to the check valve to the correct torque value.

34
00:04:17,917 --> 00:04:24,958
7. Start the locomotive and re-evaluate oil pressure to ensure proper operation of the replacement check valve.

35
00:04:24,958 --> 00:04:27,083
Victaulic Coupling Removal

36
00:04:27,083 --> 00:04:31,875
1. If required, drain oil from the lubricating oil filter housing.

37
00:04:31,875 --> 00:04:37,167
2. Remove the bolts and nuts holding the coupling halves together and remove the coupling.

38
00:04:37,167 --> 00:04:42,208
3. Slide the gaskets (one on each end of the pipe) onto the removable pipe.

39
00:04:42,208 --> 00:04:47,875
4. After the gaskets and the body of the coupling have cleared the fixed pipe, remove the pipe.

40
00:04:47,875 --> 00:04:50,542
5. Remove the gaskets from the pipe.

41
00:04:50,542 --> 00:04:53,833
6. Protect the pipe ends after disassembly.

42
00:04:53,833 --> 00:04:56,292
Victaulic Coupling Installation

43
00:04:56,292 --> 00:05:01,875
1. Inspect the gaskets, sealing surfaces of the pipe, and cleanliness of the pipe.

44
00:05:01,875 --> 00:05:09,500
2. Insert the pipe with one person holding the pipe in position while another person carefully slides the gasket into place.

45
00:05:09,500 --> 00:05:19,417
3. Install the coupling halves, then install the bolts and nuts ensuring that the oval under each bolt head is mated into the recessed oval in the coupling half.

46
00:05:19,417 --> 00:05:27,458
4. Tighten the nuts until there is a metal-to-metal contact between the coupling halves, then torque the Victaulic coupling bolts.

47
00:05:27,458 --> 00:05:32,375
5. Restore the locomotive, and with the engine at IDLE, check for oil leaks.

48
00:05:32,375 --> 00:05:36,875
6. Torque the Victaulic coupling bolts to the appropriate value.